Reconciling a pay application line by line

A pay application has to agree with itself: the continuation sheet, the summary page and the previous application. Small breaks add up.

What it is

On the AIA forms, the continuation sheet (G703) carries each schedule-of-values line: scheduled value, work completed previously and this period, materials stored, retainage. The application (G702) summarizes it: original contract sum, net change by change orders, contract sum to date, retainage, and the current payment due (line 6 minus line 7).

How Main checks it

Main checks that each line's “completed to date” equals previous plus this period plus stored, that the line totals match the summary page, that this application's “previous” matches the last application's “completed to date”, and that the contract sum to date equals the original sum plus approved changes.

A worked example Sample

SAMPLE: a synthetic project with made-up figures, to show the arithmetic. Not a real company.

Project “Eastside Parking Deck (SAMPLE)”, pay app 5, line 12 (conduit and wire):

ColumnAmount
Previously billed (app 4 completed to date)$84,600.00
This period$22,300.00
Materials stored$0.00
Completed to date, as submitted$101,900.00
Completed to date, recomputed$106,900.00

84,600 + 22,300 + 0 = $106,900.00, but the line says $101,900.00: a $5,000.00 break, likely a typed figure.

What to do

  1. Fix the line before the next application, so the error doesn't carry forward as the new “previous”.
  2. Reconcile the change-order summary on the G702 with your change-order log.

Sources

Related guides

  • Approved but unbilled change orders: An approved change is only money once it is on the schedule of values and billed. Here is how to find the ones that never got there.
  • Underbilling vs. lost revenue: Underbilling is an accounting position: earned revenue you have not billed yet. It is not money anyone owes you today. Here is the difference.
  • Retainage: Retainage is earned money held back from each payment. It is easy to lose track of once a job winds down.
  • Change-order documentation gaps: A change that is approved in one system and missing or different in another is hard to bill and easy to dispute.
  • A/R aging: Aging shows how long each invoice has been open. The useful part is knowing why each old one is still unpaid.

Check your own numbers. Upload a change-order log and pay-app lines for one project to the free check: an automated preview, not reviewed by a person.

Run the free check