Change orders with missing paperwork

A change that is approved in one system and missing or different in another is hard to bill and easy to dispute.

What it is

The same change often lives in two or three places: your change-order log, the GC's billing platform, the schedule of values. Gaps show up as a change that exists in one and not the other, a different amount, a different status, or a pending change that has waited a long time for an answer.

How Main checks it

Main matches each change across the files you send, by number first, then by amount and description, and lists every mismatch with both values side by side and the file and row each came from.

A worked example Sample

SAMPLE: a synthetic project with made-up figures, to show the arithmetic. Not a real company.

Project “Cedar Point Lab (SAMPLE)”:

ChangeYour CO logGC billing platformGap
CO-02$12,480.00$12,840.00$360.00
PCO-09Pending since Aug 9Pending review52 days without an answer
CO-11ApprovedNot listedMissing on the GC side

Three different gaps: an amount that doesn't match, a pending change waiting for an answer, and a change the GC's system doesn't have.

What to do

  1. Agree the right amount for CO-02 and correct whichever record is wrong.
  2. Ask for a decision on PCO-09 in writing.
  3. Send the executed CO-11 so it appears on the GC's side before the next pay app.

Sources