Skip to content

Help · Guide

Approved change orders that never reach a pay app

An approved change is only money once it is on the schedule of values and billed. Here is how to find the ones that never got there.

What it is

A change order is approved, the work is done, and the change never appears on the schedule of values or on a later payment application. The GC has nothing to pay because nothing was billed. On the standard AIA forms, approved changes are listed on the continuation sheet (G703) and their net total feeds line 2 of the application (G702).

How Main checks it

Main lists every approved change in your change-order log and looks for it on the schedule of values and on every pay application after its approval date, by change number first and then by amount and description. A change that appears nowhere is flagged with its approval date, its amount and the pay apps it is missing from.

A worked example Sample

SAMPLE: a synthetic project with made-up figures, to show the arithmetic. Not a real company.

Project “Harbor Street Clinic (SAMPLE)”. The change-order log has CO-07, approved on May 14 for $18,240.00. Pay apps 6, 7 and 8 were issued after that date.

Pay appPeriod endCO-07 on the SOV?CO-07 billed
6May 31No$0.00
7Jun 30No$0.00
8Jul 31No$0.00

Three pay apps after approval, CO-07 is on none of them: $18,240.00 of approved work not yet billed.

What to do

  1. Confirm the change is executed (signed), not only approved in principle.
  2. Add it to the schedule of values as its own line (AIA notes change orders are usually listed separately on the continuation sheet).
  3. Bill the completed portion on the next pay app.

Sources

Related guides

  • Underbilling vs. lost revenue: Underbilling is an accounting position: earned revenue you have not billed yet. It is not money anyone owes you today. Here is the difference.
  • Pay-app reconciliation: A pay application has to agree with itself: the continuation sheet, the summary page and the previous application. Small breaks add up.
  • Retainage: Retainage is earned money held back from each payment. It is easy to lose track of once a job winds down.
  • Change-order documentation gaps: A change that is approved in one system and missing or different in another is hard to bill and easy to dispute.
  • A/R aging: Aging shows how long each invoice has been open. The useful part is knowing why each old one is still unpaid.

See the check run. The free check runs Main’s change-order checks on a fictional SAMPLE project: an automated preview, not reviewed by a person. Reviews of real projects reopen after independent verification of the engine.

Run the SAMPLE check